Pasodale

Elementary School
8253 Mcelroy Ave.
El Paso, TX 79907
Phone: 915-434-8500
 
 
Playground Equipment Library
Kitchen/Cafeteria Classroom & Administration Remodeling
 
 
 

  New Playground Equipment
Architect: N/A
  Contractor: Lower Age Equipment - Playworld Systems
Upper Age Equipment - Landscape Structures
  Scope of work: Install two new playsets for 5-8 and 9-12 year old students.
  Start Date: February 2005
  End Date : September 2005
  Status:
                                       
    100% complete - Completed and in use.
Drawings
 

  New Kitchen/Cafeteria
Architect: Moore Nordell Kroeger Architects
  Contractor: CF Jordan
  Scope of work: Construct new kitchen/cafeteria building.
  Start Date: Fall 2006
  End Date : Summer 2007
  Status:
                                       
    100% complete - Completed and in use.
 

  New Library
Architect: Moore Nordell Kroeger Architects
  Contractor: CF Jordan
  Scope of work: Construct new library.
  Start Date: Fall 2006
  End Date : Summer 2007
  Status:
                                       
   

100% complete - Completed and in use.

 

  Classroom & Administration Remodeling
Architect: Moore Nordell Kroeger Architects
  Contractor: CF Jordan
  Scope of work: Remodel existing classrooms and administration area.
  Start Date: Summer 2007
  End Date : Fall 2007
  Status:
                                       
    100% complete - Completed and in use.
Status Pictures
Drawings
 
 

For additional bond information, please contact
Public Relations Director Patricia Ayala at (915) 434-0693 or payala@yisd.net.

Ysleta Independent School District does not discriminate on the basis of race,color, national origin, sex, disability, or age in its programs, activities or employment.

El Distrito Escolar de Ysleta no discrimina en base a raza, color, nacionalidad, sexo, discapacidad, y/o edad, en sus programas, actividades o empleo.